Project Details

  • Client

    EnerNOC
  • Service

    Self-Perform
  • Location

    Dayville, Middlefield, Cromwell, & Hartford, CT

A/Z worked closely with EnerNOC as a partner on the installation of 11 MW of demand response generation. The projects included site work, concrete, rigging, and all electrical systems for seven generators at four separate campuses for the University of Hartford. A/Z installed five 1,500 kVA Cummins generators for clients in Dayville, Middlefield, and Cromwell as well as two 2,500 kVA generators for the University. Due to the long lead time for this equipment, permitting constraints, and grant deadlines, each project presented challenging scheduling and coordination obstacles. The successful completion of each installation granted each facility with the benefit of 100% emergency power coverage. Each generator was tested and approved by CL&P as a prerequisite to DPUC grant awards. All installations were completed on active campuses without impacting daily activities.